Apr. 20, 2021 - CTH AB Public Notification

PUBLIC INFORMATION NOTIFICATION    
 
2021 CTH AB (Main Street) and CTH A (Church Road) Resurfacing
Village of Luxemburg
Kewaunee County
 
Due to the need for providing mitigation measures to prevent the spread of coronavirus, we are providing the following alternative in lieu of a Public Information Meeting so we can provide you with pertinent information and answer any questions that you may have.
 
A public information meeting will not be held to discuss the upcoming street reconstruction project in the Village of Luxemburg, Kewaunee County. This notification is being posted in order to inform the public on the scope of the project.
 
Please review this notification and if you have any comments, questions, or concerns, please mail, email or call the project manager from Robert E. Lee & Associates (REL), Mark Schuster at the contact information below by no later than May 7, 2021.
 
PROJECT LOCATION
CTH AB (Main Street), between South Village Limits and Ash Street
CTH A (Church Road), between CTH AB (Main Street) and East Village Limits
 
(SEE ENCLOSED MAP)
 

 1. PROJECT PURPOSE AND TIMELINE
 
The purpose of the project is to resurface both County Trunk Highway (CTH) AB and CTH A.  The riding surface on both roadways is in poor condition and at the end of its useful life.
 
The general contractor for the project is Dorner, Inc., Luxemburg, Wisconsin.  The paving will be completed by Northeast Asphalt from Green Bay.
 
The project will entail milling off 3-Inches of the existing asphalt surface on both of the roadways and resurfacing with new asphalt pavement.  The block on CTH AB between Robin Lane and Church Road will be regraded to create a crown in the road to improve the drainage in the area.  Additionally, damaged sections of curb and gutter will be replaced.
 
This resurfacing project is a continuation of the underground utility project that is currently being conducted in the area of Hickory and Walnut Streets.
 
Weather permitting, the curb and gutter replacement areas will be completed the week of May 10 and the resurfacing portion of the project is expected to begin around May 17 and be completed in the beginning of June.
 
 
2.  TRAFFIC CONTROL AND LOCAL ACCESS
 
The contractor is required to maintain one lane of traffic in both directions on CTH AB and on CTH A during construction.  Certain operations may require one lane to be temporarily closed with the use of flagmen.
 
Notice will be given to property owners prior to any temporary driveway closures. We ask that you do not drive on any new concrete until the contractor has removed their barriers.
 
Prior to or during construction, please notify the engineer, contractor, County or Village staff if you have a mobility issue, and they will do their best to make accommodations.
 
 
5. WORK ZONE LIMITS
 
No additional right-of-way will be acquired for the reconstruction. All work will take place within existing rights-of-way with the exception of final surface restorations, which may require access to your property.
 
 
6. RESTORATION
 
Some lawn areas behind the roadway right-of-way may be disrupted but will be restored to blend into the existing lawn grades.
 
Some driveways may require removal, which will be verified by REL and County personnel at the time of construction. Driveways and other pavements that require replacement will be replaced with the same material that currently exists.
 
 
7. FUNDING
 
The resurfacing project will be funded through a Local Roads Improvement Program (LRIP) grant and Kewaunee County funds.  There will not be any assessments or charges to the property owners along the streets.
 
 
8. ADDITIONAL CONCERNS
 
If you wish to discuss project specifics or if you wish to request a personal on-site meeting, please contact any of the people listed below, and we will be happy to accommodate your needs:

Mark Schuster, Project Manager                                           
Robert E. Lee & Associates, Inc.                              
1250 Centennial Centre Boulevard                           
Hobart, WI  54155                                                     
Phone: (920) 662-9641                                              
Email: mschuster@releeinc.com       
 
Todd Every, Highway Commissioner
Kewaunee County Highway Department
E4280 County Road F
Kewaunee, WI 54216
Phone: (920) 388-3707
Email: every.todd@kewauneeco.org